Inputs

Results update as you type. The link in the address bar keeps the inputs so you can share it.

Printed on the bag. Check the size you buy.

What this means

  • A 10 by 10 foot slab, 4 inches thick, needs about 1.36 cubic yards with 10% extra.
  • With bags that yield 0.6 cubic feet each, that is 62 bags.
  • Large pours are usually cheaper and easier as ready-mix delivered by the yard.

What if

Two inches thicker Pour 6 inches. Needs 2.04 cubic yards (was 1.36).

About this calculator

What this calculator does

It finds the volume of a rectangular slab, adds a waste allowance, and converts it to cubic yards, cubic meters, and bags.

How it is calculated

cubic feet = length * width * (thickness / 12)

with waste = cubic feet * (1 + waste / 100)

cubic yards = cubic feet / 27

bags = cubic feet / yield per bag, rounded up

How to read the result

Order ready-mix in cubic yards. For small jobs, buy the bag count, rounded up to whole bags.

Sources and method

Standard arithmetic with no outside data. The formula is shown under How it is calculated, and unit tests check worked examples, including edge cases. Bag yields come from the manufacturer data sheet.

Questions

How many cubic feet are in a cubic yard?

27, because a yard is 3 feet and 3 * 3 * 3 = 27.

How thick should a slab be?

It depends on the use and local code. Ask a contractor or your building department.

Why add waste?

Ground is rarely flat and some concrete is lost. Running short mid-pour is worse than a little extra.

Where do I find bag yield?

On the bag. Yield depends on the bag size and mix.